Saturday, 25 July 2026

New Order, Indeed

On 1 May, Manchester City Council started the process of looking into leasing out Floor 2 of Heron House, which is now No 10. North. On 11 May, it firmly committed to doing so. On 14 May, Josh Simons resigned as MP for Makerfield.

On 10 June, the Council finalised and confirmed the Heron House lease agreement. On 18 June, Andy Burnham won the Makerfield by-election. On 20 July, he became Prime Minister without a contest. On 21 July, civil servants started working at No. 10 North. 

On 24 July, Burnham officially opened No. 10 North before chairing there the inaugural meeting of the latest National Economic Council, which includes two Conservatives and six members of Reform UK, who are sitting on that Cabinet committee without reference to Kemi Badenoch or Nigel Farage.

And that, brothers and sisters, is how you stage a coup.

2 comments:

  1. Andy Burnham became Prime Minister on Monday. Within five days he opened “No.10 North” in Manchester — complete with contracts, furnishings, services, security, a logo, printed signs and banners, and held his first official meeting there.

    If anyone believes this happened spontaneously after he took office, they are kidding themselves. Secure government premises do not appear overnight. Security-cleared staff, protected communications, utilities, approved contractors, furniture, branding design, print runs and physical setup all require advance work - often months of it. Intelligence and security considerations alone make a genuine five-day turnaround from a standing start highly improbable.

    This raises obvious questions: How long have senior Labour figures been preparing the ground to remove Keir Starmer and install Andy Burnham? Was the No.10 North operation planned and advanced while Burnham was still Mayor, or while the leadership challenge was still unfolding? Government contracts, security clearances and official branding do not move at this speed without prior orchestration.

    The British public has watched a rapid transfer of power and the instant launch of a parallel Downing Street operation in the North. Mainstream coverage has largely treated the speed as unremarkable. That is not how transparent democracy usually looks.

    The No.10 North suite at Heron House was not space the government already controlled under GCHQ’s existing lease.

    GCHQ has occupied its own portion of the building (around 13,000 sq ft) since late 2019. No.10 North is using a completely separate suite of more than 4,700 sq ft that required a new sub-lease.

    That means new arrangements had to be put in place for:

    • The lease itself
    • Phone lines and secure communications
    • Utilities and services
    • Furniture and fit-out
    • Additional security and access controls
    • Reception and branding (including the logo)

    None of this happens overnight. Even a relatively simple logo involves design work, approvals and decisions about messaging and audience. Sign-offs, security clearances, procurement and physical setup all take time.

    Given the short window between Burnham taking office and the official opening, these practical steps point to preparatory work that must have started months before he became Prime Minister.